Learn / Lesson 03
Lesson 03 · 12 minutes
From drawing to work plan
Link surfaces, workholding, operations and inspection before writing a single line of program.
Build a simple map of operations and spot the information that is still missing to define the cycle.
01
Start from the required result
The drawing describes the finished part. Read diameters, lengths, bores, grooves and threads; then tolerances, datums and surface roughness. Shape alone doesn’t tell you which features are functional.
In a bushing the bore may mate with a shaft: knowing there is a bore isn’t enough, you need size, tolerance and roughness to decide how to make it and how to inspect it.
02
From stock to finished surface
The stock is the starting material; the stock allowance is the extra to remove. Roughing and finishing have different goals: remove material quickly, then reach size and roughness.
Finishing isn’t just “the last pass”: tool, allowance left, speed and feed must suit the feature you need.
03
Split the part by reachable surfaces
On paper, assign each surface to the operation in which it can be reached. Mark those near the jaws or hidden by the clamping. Then link surfaces with important relationships, such as concentricity or perpendicularity.
It often pays to machine surfaces linked by a geometric tolerance in the same clamping: every re-clamping adds a possible locating error.
04
Recognise the operation families
Facing, OD turning, drilling and boring, grooving, threading and parting-off: each has its own tools and logic. Live-tool operations require a machine set up for them.
Use these names to describe the plan, without choosing codes or parameters yet. A good plan can be understood without reading the program.
05
Put inspection into the plan
For each important feature ask what to measure, with which instrument and in which operation. An in-process check gives you information before a surface becomes hard to reach.
Size, geometric tolerance and roughness are different requirements and aren’t checked with the same instrument. That is exactly the logic of the inspection sheet in the kit.
?
Exercise: fill in three lines
- Line 1 · the stock and the data missing from the drawing.
- Line 2 · the surfaces assigned to each operation.
- Line 3 · the features to inspect and in which operation they can be reached.
Scenario: a bushing with a through bore, an outside diameter and two faces. A good answer points out, for example, that the bore tolerance is missing or that no datum is defined for overall length.
✓
Test yourself
Three quick questions. Get them all right and the lesson is marked as completed on this device.
Where does the work plan start?
Does a shiny surface prove the diameter is right?
When should inspection be planned?
Lesson completed.
≡
Take it to the shop floor
- Drawing, stock, workholding, operations and inspection form a chain.
- The program carries out a strategy that must already be clear on paper.
- Cycle time is optimised after the good part is guaranteed.
↗
Further reading
Machine builders’ pages are quoted as examples: for your machine, always follow the manual and data sheets of the specific model.